This estimating technique is based on a total quantity of budget to test the entire test object. The total amount is divided over the distinguished components. When dividing the total budget over the various components, the allocated risk class (for a test strategy) and the size of the components are taken into account. A factor is chosen for each risk class (in the test strategy) that enables a weighted distribution. For example:
The steps to derive an estimate are as follows:
An example to clarify this: 100 hours are to divided over 5 object parts. The size and a risk class have been determined for each object part. The number of hours per object part is then established following the steps above.
Overview – Building Block
EstimatingRelated Wiki’s
Estimation based on ratios
Estimation based on test object size
Work Breakdown Structure
Evaluation estimation approach
Proportionate estimation
Extrapolation
Test Point Analysis (TPA)